Question: Assignment Project activities, precedence and times are shown below. table [ [ Activity , Precedence,Time, weeks ] , [ A , - , 5

Assignment
Project activities, precedence and times are shown below.
\table[[Activity,Precedence,Time, weeks],[A,-,5],[B,A,7],[C,B,3],[D,C,5],[E,C,1],[F,B,2],[G,D,E,F,1],[H,G,1]]
PLEASE GO THRU THE LECTURES/NOTES BEFORE ATTEMPTING THE QUESTIONS.
a. Draw EARLY start Gantt chart.
b. Name the CRITICAL activities
c. Draw LATE start Gantt chart.
d. Draw AON forward pass.
e. Draw AON backward pass.
f. Develop the SLACK calculation chart.
g. Identify the CRITICAL path.