Question: Assignment Project management ( no uncertainty ) Question 1 Activity Time ( days ) Precedence ( A ) Party Planning ( e . g .

Assignment Project management (no uncertainty)
Question 1
Activity Time (days) Precedence
(A) Party Planning (e.g. Event Theme, # of Guests)5
(B) Arrange Partys Venue 10(A)
(C) Hire Caterer / Bartender 5(A)
(D) Hire a Band 7(A)
(E) Select, Address & Send Invitations 3(B)
(F) Plan Food & Drink Menu 6(C)
(G) Band Practice Set List 10(D)
(H) Confirm Guest List (RSVP)15(E)
(I) Off-site Food & Drink Preparation 12(H),(F)
(J) Venue Set-Up 2(G),(I)