Question: Assignment Tasks: Answer the following, given the following table including project plan: ID Task name Duration Resources predecessors 1 Create business plan 5 days Project
Assignment Tasks:
Answer the following, given the following table including project plan:
| ID | Task name | Duration | Resources | predecessors |
| 1 | Create business plan | 5 days | Project Manager |
|
| 2 | Get business license | 1 day | Project manager, VP | 1 |
| 3 | Set up bank account | 1 day | VP | 2 |
| 4 | Get funding | 21 days | Employee, VP | 2,3 |
| 5 | Pick a business location | 5 days | PM, VP | 4 |
| 6 | Set up office equipment and furniture | 2 days | Employee | 5 |
| 7 | Hire team | 10 days | PM | 6 |
| 8 | Run promotion | 4 days | PM, VP, employee | 7 |
- Apply variety techniques (MS Project) in managing, monitoring and controlling teams and project: [10 Marks]
- Create the project plan using MS project.
- Add the duration, start date, end date, resources, predecessors to the project plan.
- View the network diagram for the project plan.
- Create a copy of standard calendar named ProjectCal and apply it to the project
- Create a filter to define the tasks that uses the employee as a resource name it ERes filter.
Step by Step Solution
There are 3 Steps involved in it