Question: Assignment Tasks: Answer the following, given the following table including project plan: ID Task name Duration Resources predecessors 1 Create business plan 5 days Project

Assignment Tasks:

Answer the following, given the following table including project plan:

ID

Task name

Duration

Resources

predecessors

1

Create business plan

5 days

Project Manager

2

Get business license

1 day

Project manager, VP

1

3

Set up bank account

1 day

VP

2

4

Get funding

21 days

Employee, VP

2,3

5

Pick a business location

5 days

PM, VP

4

6

Set up office equipment and furniture

2 days

Employee

5

7

Hire team

10 days

PM

6

8

Run promotion

4 days

PM, VP, employee

7

  1. Apply variety techniques (MS Project) in managing, monitoring and controlling teams and project: [10 Marks]
  • Create the project plan using MS project.
  • Add the duration, start date, end date, resources, predecessors to the project plan.
  • View the network diagram for the project plan.
  • Create a copy of standard calendar named ProjectCal and apply it to the project
  • Create a filter to define the tasks that uses the employee as a resource name it ERes filter.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!