(assume 6 min. per vehicle, 15 stations) Concept hourly capacity = 15 stations x 4 vehicles/hour= 60...
Fantastic news! We've Found the answer you've been seeking!
Question:
(assume 6 min. per vehicle, 15 stations)
Concept hourly capacity = 15 stations x 4 vehicles/hour= 60 vehicles per hour that could be tested assuming no delays.
What would be the daily capacity of the testing site assuming a 10 hour workday = 100
Assume 25 feet per vehicle.
Concept includes 4,000 feet of total queuing (2 lanes @ 2,000 feet each) from entry point at street to testing station.
This allows for ______ vehicles that can queue (_____ feet/ ____ feet per vehicle)
Once filled, the last vehicle in the queue would have an approximate _____ minute wait time