Question: Assume a company s activity - based costing system includes three activities. The following information is available with respect to those activities: Activity Cost Pool

Assume a companys activity-based costing system includes three activities. The following information is available with respect to those activities:
Activity Cost Pool Estimated Overhead Cost Expected Activity
Testing $ 150,000100,000 testing minutes
Setups $ 149,6002,200 setup hours
Molding
$ 220,000
10,000
machine hours
What is the activity rate for the Setups activity?
Multiple Choice
$58 per setup hour
$68 per setup hour
$78 per setup hour
$88 per setup hour