Question: Assume a company's activity-based costing system includes three activities with the following activity rates: Two of the company's many products include Product A and Product

Assume a company's activity-based costing system includes three activities with the following activity rates: Two of the company's many products include Product A and Product B. These two products consumed the company's activities as follows: If the company makes 50 units of Product A and this product's direct material cost per unit is $14 and its direct labor cost per unit is $10, then what is the total product cost assigned to Product A? Multiple Choice $2,990 $3,190 52,890 If the company makes 50 units of Product A and this product's direct material cost per unit is $14 and its direct labor cost per unit is $10, then what is the total product cost assigned to Product A? Multiple Choice $2,990 $3,190 $2,890 $3.390