Question: Assume a companys activity-based costing system includes three activities with the following activity rates: Activity Cost Pool Activity Rate Travel $ 2 per mile driven

Assume a company’s activity-based costing system includes three activities with the following activity rates:

Activity Cost PoolActivity Rate
Travel$ 2per mile driven
Deliveries$ 50per delivery
Customer service$ 22per phone call

Two of the company’s many customers include Customer A and Customer B. These two customers consumed the company’s activities as follows:

 Total Expected Activity
Customer ACustomer B
Travel (number of miles driven)310250
Deliveries (number of deliveries)155
Customer service (number of phone calls)2012

How much cost would be assigned from the Travel activity to Customer A?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

ANSWER To calculate the cost assigned from the Travel activity to Customer A we multiply t... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!