Question: Assume a four-step batch process is worked in series; that is, work moves from workstation 1 to workstation 2, to workstation 3, and then to
Assume a four-step batch process is worked in series; that is, work moves from workstation 1 to workstation 2, to workstation 3, and then to workstation 4. Each workstation requires a setup before it begins work on the next batch. Assume each workstations setup time and task time are different from the others. As batch size changes, is it possible for the bottleneck to move from one task to another?