Question: Assume all jobs are available for processing at present time, which is day O. Due date is defined as the number of days from preset
Assume all jobs are available for processing at present time, which is day O. Due date is defined as the number of days from preset time. Processing Time (days) Job A B C D E 12 15 6 Due Date (days) 15 27 18 9 8 Under SPT rule, the flow time of job B is (type number only, no text)
Assume all jobs are available for processing at present time, which is day 0 . Due date is defined as the number of days from preset time. Under SPT rule, the flow time of job B is (type number only, no text)