Question: Assume it's announced at the start that the project needs to be done a week faster than planned. ID Min Months 2 B Task Construct

Assume it's announced at the start that the
Assume it's announced at the start that the project needs to be done a week faster than planned. ID Min Months 2 B Task Construct bus frame Prepare seat connectors Produce collapsible seats Produce regular seats Final assembly Crash $ $350,000 $50,000 $120,000 $130,000 $50,000 1 3 2 2 C What is the crash cost per month for task A? (8) Which task should be crashed first to get done a month faster? 19 If the airport will pay a $10.000 bonus to get the project done an additional month faster. Is it worth trying? [10]