Question: Assume that operations on a work package were expected to cost $1500 to complete the package. They were originally scheduled to have been finished today.
Assume that operations on a work package were expected to cost $1500 to complete
the package. They were originally scheduled to have been finished today. At this point,
however, we have actually expended $1350, and we estimate that we have completed
two-thirds of the work. What are the Cost and Schedule variances? Calculate CPI, SPI,
ETC & EAC. Interpret the results (what does it all mean).