Assume that Systems Analysis actually finished at 8 weeks, Design Input & Output actually finished at 15
Fantastic news! We've Found the answer you've been seeking!
Question:
Assume that "Systems Analysis" actually finished at 8 weeks, "Design Input & Output" actually
finished at 15 weeks, and "Design Database" actually finished at 19 weeks. Recalculate the
expected project completion time. Which activities would you focus on to get the project back
on schedule?