Question: Assume that tasks A and B are predecessors to task C. When performing a forward pass calculation in the network, the value carried forward as

Assume that tasks A and B are predecessors to task C. When performing a forward pass calculation in the network, the value carried forward as the Early Start of task C is ________. Group of answer choices The smallest late finish of tasks A and B None of the above The largest early finish of tasks A and B The largest late finish of tasks A and B The smallest early finish of tasks A