Question: Assume that we plan to construct a house. The construction requires the following activities with fixed durations and precedence constraints. The numbers near each activity

Assume that we plan to construct a house. The construction requires the following activities with fixed
durations and precedence constraints. The numbers near each activity represent its durations (in days).
Note that the schedule has 3 constraints. Perform all the CPM computations as taught in lecture, incl. ES, EF,
LS, LF, Project Duration and FF/TF for each activity. Label accordingly. Highlight the critical path and specify
project duration (if applicable). Answer the following questions for all of them. Answers must be entered
and submitted in the answer sheet found in Canvas.
What is the ES of activity painting?
What is the EF of activity Painting?
What is the LS of activity Garden?
What is the free float of activity Faade?
What is the total float of activity Faade?
What is the free float of activity Windows?
What is/are the activity(ies) with the largest free float?
What is/are the activity(ies) with the largest total float?
What is the FF of activity Ceiling?
What is the total float of activity Carpentry?
 Assume that we plan to construct a house. The construction requires

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!