Question: Assume that we plan to construct a house. The construction requires the following activities with fixed durations and precedence constraints. The numbers near each activity
Assume that we plan to construct a house. The construction requires the following activities with fixed
durations and precedence constraints. The numbers near each activity represent its durations in days
Note that the schedule has constraints. Perform all the CPM computations as taught in lecture, incl. ES EF
LS LF Project Duration and FFTF for each activity. Label accordingly. Highlight the critical path and specify
project duration if applicable Answer the following questions for all of them. Answers must be entered
and submitted in the answer sheet found in Canvas.
What is the ES of activity painting?
What is the EF of activity Painting?
What is the LS of activity Garden?
What is the free float of activity Faade
What is the total float of activity Faade
What is the free float of activity Windows?
What isare the activityies with the largest free float?
What isare the activityies with the largest total float?
What is the FF of activity Ceiling?
What is the total float of activity Carpentry?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock