Question: Assume that you are leading the team developing the foundation for a new home. You were provided a schedule to guide the effort, but the
Assume that you are leading the team developing the foundation for a new home. You were provided a schedule to guide the effort, but the schedule you were given did not include resources. What could you conclude about what might happen to the proposed schedule duration and budget once resources are applied? Also, in your opinion, is it wise to accept a schedule prior to the assignment of project resources? Why, or why not?