Question: Assume that you graph the changes in net present value against the changes in the value of a single variable a project. The steepness of
Assume that you graph the changes in net present value against the changes in the value of a single variable a project. The steepness of the resulting function illustrates the:
A degree of operating leverage within the project.
B tradeoff of variable versus fixed costs utilized by the project.
C range of total outcomes possible from accepting a proposed project.
D contribution margin of the project at various levels of output.
E degree of sensitivity of a project's outcome to a single variable of the project.