Question: Assume the following informalion: table [ [ , Hours ] , [ Queue tine, 3 3 ] , [ Wait tine, 2 4 ]

Assume the following informalion:
\table[[,Hours],[Queue tine,33],[Wait tine,24],[Process tine,2],[Move tine,2],[Inspection tire,4]]
The delivery cycle lime is:
 Assume the following informalion: \table[[,Hours],[Queue tine,33],[Wait tine,24],[Process tine,2],[Move tine,2],[Inspection tire,4]] The