Assume the following information:
Actual run time this week 4,500 minutes
Machine time available this week 5,000 minutes
Actual run rate this week 3.6 units per minute Ideal run rate 4.0 units per minute
Defect-free output this week 15,000 units
Total output this week (including defects) 16,200 units
What is the utilization loss in units?
Multiple Choice
2,000 units
1,000 units
2,500 units
5,000 units