Question: Assume there is specialized, dedicated staff for each specific task and they can only work on 1 project at a time. For example, only 1
Assume there is specialized, dedicated staff for each specific task and they can only work on 1 project at a time. For example, only 1 project brief can be developed at a time, only 1 photoshoot can occur at a time, etc.

Reference the Marketing Campaign Critical Path
What is the flow time to create a new marketing campaign?
Group of answer choices
8 days
6 days
4 days
7 days
5 days
Duration Task Label Task Description (Days) A Project Brief 1 B Photoshoot 6 Purchase Media 4 D Website Updates 2 E Final Approval 1 F Launch 1 Predecessor None A A A CD BE FStep by Step Solution