Question: Assume we have 2 assembly lines for process Two identical sandwich lines Lines have two workers and three operations All completed sandwiches are wrapped

Assume we have 2 assembly lines for process Two identical sandwich lines Lines have two workers and three operations All completed sandwiches are wrapped First assembly line Bread Toaster 15 sec/sandwich 20 sec/sandwich 40 sec/sandwich Order 30 sec/sandwich Bread Fill Toaster 15 sec/sandwich 20 sec/sandwich Find: a) Process cycle time. b) Bottleneck c) Capacity per hour. Second assembly line Copyright 2020 Parson Canada Inc 40 sec/sandwich Wrap/Deliver 37.5 sec/sandwich
Step by Step Solution
There are 3 Steps involved in it
To solve the problem we will analyze each step in the assembly lines Step 1 Calculate the Process Cy... View full answer