Question: - Assume you are the project manager and based on your customer's requirements you have determined there are four main tasks in a Dream Backyard

 - Assume you are the project manager and based on your

- Assume you are the project manager and based on your customer's requirements you have determined there are four main tasks in a Dream Backyard project. Each phase has been assigned a TBC. Specifically, the customer wants a pool and spa built (Task 1$50,000 ); all plumbing, electrical, and mechanical installed (Task 2 - \$20,000); a pool deck with planters and a raised fire pit (Task 3$15,000 ); and landscaping and clean up (Task 4 $5,000 ). You estimate this will take 5 weeks to complete. The costs are budgeted as follows: What is the total cumulative TBC? What is TBC at the end of week 4 ? - Assume 4 weeks have passed and these are the actual costs per week: What is the CAC at the end of week 4 ? Below is the cumulative percentage of work complete per task per week: What are the CEV, CPI, and CV at the end or week 4 ? What is the SPI

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!