Question: Assume you are the project manager for a software project. You have been asked to calculate the expected cost for the project. Your company's database
Assume you are the project manager for a software project. You have been asked to calculate the expected cost for the project. Your company's database indicates that developers can handle 10 function points each person-month and that the cost per developer at your firm is $65,000 per month. You and your team of 6 developers have come up with the following requirements: What is the estimated months for the projectrduration? (round the final answer to wo decimal places.)