Question: Assume you are the Project Manager for CRM implementation project . One of your project team members tells you that the project is a super

Assume you are the Project Manager for CRM implementation project . One of your project team members tells you that the project is a super success because the project was supposed to be done in 10 weeks with total budget of CA$ 90,000. Now, project team is at the end of Week 7 and they have spent CA$ 65,000 and 35% of project is remained.
A) Canulate CV and SV for this project. Show all you calculation [2 marks]
B) What is your opinion about what your colleague is saying? Explain your answer based on the values of CV and SV [1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!