Question: Assume you have compiled the steps needed to complete a project as noted below. You have identified all relevant steps and have made some determination

Assume you have compiled the steps needed to complete a project as noted below. You have identified all relevant steps and have made some determination regarding predecessor/successor relationships. Suppose that you have defined duration estimates to each of the activities as shown in the table. Recreate the Network diagram for this project and note how MS Project uses nodes to identify activity durations, start and finish dates, and predecessors. What is the critical path for this network diagram? How do we know?
Activity Duration Predecessors
A - Survey site 5 days
-
B - Install sewer and storm drainage
9
days
A
C - Install gas and electric power lines
4
days
A
D - Excavate site for spec house
2
days
B, C
E - Pour foundation
2 days
D
 Assume you have compiled the steps needed to complete a project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!