Question: Assume you have compiled the steps needed to complete a project as noted below. You have identified all relevant steps and have made some determination
Assume you have compiled the steps needed to complete a project as noted below. You have identified all relevant steps and have made some determination regarding predecessorsuccessor relationships. Suppose that you have defined duration estimates to each of the activities as shown in the table. Recreate the Network diagram for this project and note how MS Project uses nodes to identify activity durations, start and finish dates, and predecessors. What is the critical path for this network diagram? How do we know?
Activity Duration Predecessors
A Survey site days
B Install sewer and storm drainage
days
A
C Install gas and electric power lines
days
A
D Excavate site for spec house
days
B C
E Pour foundation
days
D
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
