Question: Assume you have reviewed your most recent project performance report and determined that your project is currently experiencing schedule performance problems. Which of the following

Assume you have reviewed your most recent project performance report and determined that your project is currently experiencing schedule performance problems. Which of the following strategies represents a potential strategy to improve your schedule performance?
Group of answer choices
Overlap activities when possible.
Reduce resources to extend the duration of selected activities.
Restrict requests for overtime.
Examine resource needs and replace rapid, proficient workers with less expensive and less experienced workers.