Question: Assume you have two projects X and Y. Net present value of X: and Y is $10 and $12, if they are mutually exclusive what
Assume you have two projects "X" and "Y". Net present value of "X: and "Y" is $10 and $12, if they are mutually exclusive what project do you choose? Assume you have no more information.
| 1. | X |
| 2. | Y |
| 3. | Both |
| 4. | None |