Question: Assuming that the data given below is information in the learning curve for an employee in producing a particular product. Unit # ANAAN28 12
Assuming that the data given below is information in the learning curve for an employee in producing a particular product. Unit # ANAAN28 12 14 16 20 24 30 Time (Hour) 683333539 107 80 64 60 55 51 48 46 a- Do you think that this employee can meet a demand of 10 units in three months if he works 8 hours a day? b- If not, how many units he can produce within 3 months. c- How should the learning curve of the employee to produce 10 units within 4 months
Step by Step Solution
3.34 Rating (151 Votes )
There are 3 Steps involved in it
Solution The formulas are let x be the learning percentage Time to produce nth UnitT... View full answer