Question: Assumptions: 1 . There will be two specialized crews concurrently available for Excavation andFormwork placement activities ( e . g . , Crew B 1
Assumptions: There will be two specialized crews concurrently available for "Excavation" and"Formwork placement" activities eg Crew B: responsible for activity B Crew B: responsible for activity B etc.; however, for "Site leveling", "Reinforcement installation" and "Casting concrete" activities, there will only be a single specialized crew available egCrew C: responsible for both activities Cl and C An hour working schedule is considered Quantities and as a result the durations for the identical activities will be the same for both the houses In earth works activities, the compacted volume of soil will remain the same as its bank volume For the "Site leveling" activities, only the overall additional or required quantity of soil that needs to be removed from or brought to the construction site must be used for estimation of the duration.Requirements:You are asked to perform the following operations:a Define and tabulate the logical relationships ie list of predecessors among the activities.b Construct the ActivityonArrow AOA network for the whole project, comprising construction of houses.c Calculate Early Event Times EET Late Event Times LET and Total Project Time TPT ie fillin the AOA network developed in "Part bd Determine Late Start Time LST of only "Formwork placement" activity of the first house.e Determine by how many days can "Casting concrete" activity of the first house be delayed without affecting the Early Start Time EST of any of its succeeding activities.f Determine the total cost of the project by assuming an indirect cost IC of $day
Goal:
The purpose of this assignment is to develop a deeper understanding of estimating quantities for a construction project, to practice network analysis, also to present calculations in the form of reports.
Description:
A small project comprises the construction of two identical houses on a single parcel. Project includes a site leveling activity and each house consists of excavation, reinforcement installation, formwork placement, and casting concrete activities. The activities and the associated direct cost DC of each activity are given in the following table.
tableActivity,Description,Cost $ASite leveling,House BExcavation,CReinforcement installation,DFormwork placement,ECasting concrete,House BExcavation,CReinforcement installation,DFormwork placement,ECasting concrete,
The quantity of earth works for "Site leveling" activity needs to be estimated with respect to the grid view shown in Fig. and by using the "Grid Method". Fig. displays a grid survey of levels taken on the construction site which is required to be brought to a level of Quantity of earth works for "Excavation" activity should be determined by using the dimensions of the trench shown in Fig. with a width and a depth of and respectively. Quantities for "Reinforcement installation", "Formwork placement", and "Casting concrete" activities are already estimated as tons, and respectively. The crew assigned for "Site leveling" activity is formed of Trucks and Graders which can work with an output rate of
Productivity for "Excavation" activity is estimated to be manhours and a crew formed of Labors and General Foremen is assigned for this activity. Crew assigned for "Reinforcement installation" activity is formed of Steel Workers and Labors which can work with an output rate of tonday Productivity for "Formwork placement" activity is estimated to be manhours and a crew formed of Carpenters and General Foreman is assigned for this activity. Productivity for "Casting concrete" activity is estimated to be manhours and a crew formed of Concrete Workers is assigned for performing it
Figure Grid view of the construction site
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock