Question: ASX-listed ABC Mining has recently completed an updated Ore Reserve estimate for the company's flagship base metal project in South Australia (a significant project). The
ASX-listed ABC Mining has recently completed an updated Ore Reserve estimate for the company's flagship base metal project in South Australia (a significant project). The update has resulted in a material change in the estimated tonnage and grade of the Ore Reserve. The Ore Reserve was estimated by a Competent Person and classified in the Probable and Proved categories. ABC has previously reported the Mineral Resources that underpin the Ore Reserves, and Exploration Results on which the Mineral Resource estimate is based, to the market in accordance with the JORC Code (2012). Is ABC required to attach a JORC Table 1 to the Public Report when it discloses the updated Ore Reserves? If not, why not? If yes, which sections are required and how would these be included?
Step by Step Solution
There are 3 Steps involved in it
YesABC Mining is required to attach a JORC Table 1 to the Public Report when it discloses the updated Ore Reserves for its flagship base metal project... View full answer
Get step-by-step solutions from verified subject matter experts