Question: At a specific construction site, soil excavated from a borrow site and used as a fill. The borrow site water content is 2 6 %

At a specific construction site, soil excavated from a borrow site and used as a fill. The
borrow site water content is 26% and the solids specific gravity is 2.65. Standard Proctor
Compaction tests resulted in a maximum dry unit weight of 105pcf at optimum moisture
content of 20%. Contract specifications require 95% relative compaction. However, at the
site, the contractor complains that the fill pumps and ruts badly before reaching the required
dry unit weight.
a. Draw the zero air voids curve for the fill soil (use spreadsheet).
b. What is the maximum possible water content at 95% relative compaction?
c. If the soil is compacted at the natural water content of 26%, what is the maximum
possible dry unit weight (without pumping)?
d. Briefly explain if the contractors' argument is valid?
At a specific construction site, soil excavated

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!