Question: At an IRS printing facility forms are printed in batches of 1200 units. Processing a batch involves a software setup time of 20 minutes and
At an IRS printing facility forms are printed in batches of 1200 units. Processing a batch involves a software setup time of 20 minutes and a runtime of 1 second per form.
With new software setup time could be reduced to 10 minutes. Assuming a batch size of 1200 units, how does the capacity of this process (in forms per 8 hour day) change?
a. Decreases by 1000 forms
b. No change
c. Decreases by 4800 forms
d. Increases by 4800 forms