Question: At Countywide Construction you decide to use a very simple commercial construction product. with eight tasks as follows: Prepare the foundation (10 days). Then assemble
At Countywide Construction you decide to use a very simple commercial construction product. with eight tasks as follows: Prepare the foundation (10 days). Then assemble the building When the building is assembled, start two tasks at once: Finish the Interior work (4 days) and set up an appointment for the final building inspection When the Interior work is done, start two more tasks at once: landscaping and driveway paving When the landscaping and driveway are done, do the painting Finally, when the painting Is done and the final Inspection has occurred, arrange the sale Draw a diagram for the project tasks to show how many days It will take to complete the project? What is the critical path