Question: at position 3 You complete your PERT calculations for your project and you have determined your expected duration is 57 weeks with a standard deviation

at position 3 You complete your PERT calculations for your project and you have determined your expected duration is 57 weeks with a standard deviation of 1.81. You want your project to complete on your end date with a 60% probability. How many weeks before your goal end date do you begin your project