Question: At the beginning of 2017, Solid foundation entered into a contract to build a network for Optus Inc. This project will take two years to
At the beginning of 2017, Solid foundation entered into a contract to build a network for Optus Inc. This project will take two years to complete. Assume that total revenue from the project is expected to be $8,000,000 and expected cost is $ 6,000,000. Cost incurred during 2017 is $ 3,000,000. Assume that the company estimates percentage complete based on costs incurred as a percentage of total estimated costs. If Solid foundation uses the completed contract method, how much revenue will be reported in 2017?
$6,000,000.00 $4,000,000.00 None. $3,000,000.00
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
