Question: At the moment there are only three projects which are: renovation of the squash court which will cost R 2 4 5 0 0 ,
At the moment there are only three projects which are: renovation of the squash court which will cost R building braai facilities which will cost R and erecting undercover packing for staff members which will cost R
The projects have to be measured according to the following criteria: skills, budget, and time. It has been found out that the renovation of the squash court will take longer, followed by parking area and braai facilities respectively. The Military Academy will have more skills on building braai facilities, followed by renovation of the squash court and parking area respectively. The weights are allocated to the criteria as follows: Budget, Skills and
Time
a Calculate the best project without making use of weights allocated.
b Calculate the best project if weight is taken in consideration.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock