Question: a)The expexted (estimated time for activity C is ______ weeks. b)The variance for activity C is _____ weeks. c)Based on the caculation of the estimated
a)The expexted (estimated time for activity C is ______ weeks.
b)The variance for activity C is _____ weeks.
c)Based on the caculation of the estimated times, the critical path is _____?
1. A-B-E-F-I-K
2. A-C-F-I-K
3. A-C-F-H-J-K
4. A-B-E-F-H-J-K
5. A-D-J-K
6. A-B-E-G-J-K
7. A-C-G-J-K
d) The estimated time for the critical path is _____?
e) The activity variance along the critical path is ____?
f) The probability that Hopkins will finish the project in 40 weeks of less is ______.