Question: Atkinson Landscaping applies variable overhead based on direct labour hours. At the beginning of the current year, Atkinson had estimated the following: Estimated variable overhead
Atkinson Landscaping applies variable overhead based on direct labour hours. At the beginning of the current year, Atkinson had estimated the following:
Estimated variable overhead $56000
Estimated units of production $10000 units
Standard direct labour hours per unit 2.5 hours
During the year, 11 000 units were produced using a total of 27 200 direct labour hours and actual overhead costs were $60 000. Atkinsons variable overhead spending variance for the year was:
a. $ 672 F
b. $ 928 F
c. $4000 U
d. $ 145 U
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts