Question: audrey ross, operations manager for BCD technologies, must schedule work for the next five days. Each unit takes 2 0 minutes to process. Available capacity

audrey ross, operations manager for BCD technologies, must schedule work for the next five days. Each unit takes 20 minutes to process. Available capacity is 8 hours per day. The production order quantities are 18,28,38,16 and 20 for Monday through Friday, respectively. What should be the plan for Wednesday? a. move 4 units to tuesday and 10 units to thursday 2. move 8 units to monday ,8 units to thursday 3. move 8 units to thursday and 4 units to friday 4. move 2 units to monday, 8 units to thursday and 4 units to friday