Question: A+UM+ Question 1) Activity Predecessor Optimistic Most Pessimistic Likely A 5 7 15 B 14 21 22 C 21 33 45 D A 14

A+UM+ Question 1) Activity Predecessor Optimistic Most Pessimistic Likely A 5 7

A+UM+ Question 1) Activity Predecessor Optimistic Most Pessimistic Likely A 5 7 15 B 14 21 22 C 21 33 45 D A 14 16 30 E B 18 19 26 F B 7 9 11 G B. C 7 9 17 D 8 8 8 I D, E 3 4 5 F. G 4 5 6 K H. I 7 8 21 a) (10 points) Develop an AOA diagram for the given activities. b) (5 points) Find the critical path and project completion time. c) (10 points) Find the probability of completing the project at 58 days. d) (10 points) The project manager is promised $12,000 if the project completed in less than 50 days, $8,000 if the project completed within 50-53 days, and no reward if the project goes above 53 days. What is the expected value of the manager's bonus?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!