Question: a-Using Table 1 draw the network , find the critical path using CPM.Set up the LP model and find free float and total float.Draw the

a-Using Table 1 draw the network , find the critical path using CPM.Set up the LP model and find free float and total float.Draw the network similar to the figure in the Figure 1a-Using Table 1 draw the network , find the

Table 1

Activity Predecessor Duration
A - 10
B - 7
C A,B 5
D A,B 3
E C 4
F C,D 3
G F 14

b-If we want to complete the project in 25 days,Set up the LP model using Table 2

Table 2

Activity

Reduction Cost

Max Possible Reduce Time

A

20

2

B

30

2

C

40

2

D

10

2

E

50

2

F

30

2

G

20

2

c-If project due date is 30 , find the probability of project completion type at 30 days using Table 3 with PERT method

Table 3

Activity Predecessor Duration a b m
A - 10 8 12 10
B - 7 4 10 7
C A,B 5 4 6 5
D A,B 3 2 4 3
E C 4 2 6 4
F C,D 3 1 5 3
G F 14 8 20 14

*

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!