Question: a-Using Table 1 draw the network , find the critical path using CPM.Set up the LP model and find free float and total float.Draw the
a-Using Table 1 draw the network , find the critical path using CPM.Set up the LP model and find free float and total float.Draw the network similar to the figure in the Figure 1
Table 1
| Activity | Predecessor | Duration |
| A | - | 10 |
| B | - | 7 |
| C | A,B | 5 |
| D | A,B | 3 |
| E | C | 4 |
| F | C,D | 3 |
| G | F | 14 |
b-If we want to complete the project in 25 days,Set up the LP model using Table 2
Table 2
| Activity | Reduction Cost | Max Possible Reduce Time |
| A | 20 | 2 |
| B | 30 | 2 |
| C | 40 | 2 |
| D | 10 | 2 |
| E | 50 | 2 |
| F | 30 | 2 |
| G | 20 | 2 |
c-If project due date is 30 , find the probability of project completion type at 30 days using Table 3 with PERT method
Table 3
| Activity | Predecessor | Duration | a | b | m |
| A | - | 10 | 8 | 12 | 10 |
| B | - | 7 | 4 | 10 | 7 |
| C | A,B | 5 | 4 | 6 | 5 |
| D | A,B | 3 | 2 | 4 | 3 |
| E | C | 4 | 2 | 6 | 4 |
| F | C,D | 3 | 1 | 5 | 3 |
| G | F | 14 | 8 | 20 | 14 |
*