Question: Average lead time (LT) is 20 days, with a std. dev.(LT) of 6 days. Daily demand (d) is 50 units (constant). Find safety stock (SS)

 Average lead time (LT) is 20 days, with a std. dev.(LT)

Average lead time (LT) is 20 days, with a std. dev.(LT) of 6 days. Daily demand (d) is 50 units (constant). Find safety stock (SS) and reorder point (ROP) for z=2. SS=900 units, ROP =1,900 units SS=600 units, ROP=1,600 units SS=600 units, ROP =1,000 units SS=80.5 units, ROP=1,080.5 units SS=53.7 units, ROP=1,053.7 units