Question: Awesome company makes two products: E and F. Data for two products for year: Current Selling price per unit E($275) F($200) Current materials cost per

Awesome company makes two products: E and F. Data for two products for year:


Current Selling price per unit E($275) F($200)

Current materials cost per unit E($10) F($9)

Current labor cost per unit E($12) F($10)

Current labor hours per unit E(8.5) F($4.5)

Number of units produced E(2500) F(1500)

The companys manufacturing overhead costs for the year are $300,000. Management is considerings an activity based costing sytem in which 35% of the overhead would continue to be allocated on the basis of direct labor hours and 65% would be allocated on the basis of machiine hours.

The time is expected to be distributed as follows for upcoming year:

Machine related E(2,000) F(1,000)

1) Compute the overhead cost per unit using the proposed ABC system:

Product E 

Product F 

2) Compute the unit product cost per unit using the proposed ABC system:

Product E 

Product F 

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Computing the overhead cost per unit using the proposed ABC system First we need to calculate the to... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!