Question: a)What is the total cost required for completing this project on normal? b)if you wish to reduce the time required to complete this project by

a)What is the total cost required for completing this project on normal?
b)if you wish to reduce the time required to complete this project by 1 day ( from 21 to 20), which activity(ies) should be crashed?
c) if you wish to reduce the time required to complete this project by 1 additional day ( from 20 to 19), which activity should be crashed?
d)If you wished to reduce the time required to complete this project by 1 by 1 additional day ( from 19 to 18), which activity should be crashed?
e)what is the minimum completion time achievable for this project
Development of a new software is being considered by company. The activities necessary for the completion of this project are listed in the following table, ACTIVITY IMMEDIATE Normal PREDECESSORS Time (DAS) Crash Time (Bays) Normal Cost Crash Cost 6 5 3 B 5 4000 5000 4500 3000 A 3 c D 5500 6000 5500 4000 4500 B 5 4 E F G 6 5 6 C AD EF 2500 5000 5 4 7000 7000 7000