Question: ( b ) [ 1 5 Points ] You are the GC and you have taken a $ 2 0 0 million project on a

(b)[15 Points] You are the GC and you have taken a $200 million project on a cost plus 5%
with a GMP of $210 million and 50% share of the Value Engineering Savings. You complete
the project at $180 million. How did the owner and the GMP contractor finally make out in
terms of dollars?
Owner paid: $_____________
GMP Contractor received: $_______________