Question: B 10 A 7 D Activity Duration 3 6 Crash Activity Slope ($/day) Max Crash Time (days) A 15 13 B 3 8 D 17

B 10 A 7 D Activity Duration 3 6 Crash Activity

B 10 A 7 D Activity Duration 3 6 Crash Activity Slope ($/day) Max Crash Time (days) A 15 13 B 3 8 D 17 The total project duration needs to be reduced by 2 days) Given the preceding network and table of crash costs, determine the total crash cost based on che most economical approach