Question: B, 8 E, 7 - AS C, 9 F,7 H6 G4 D. 8 1. A project network is given by the following table Draw the

B, 8 E, 7 - AS C, 9 F,7 H6 G4 D. 8 1. A project network is given by the following table Draw the network above and all path lengths and answer the following: The minimum time required to complete the project is: -The early start time (ES) for job G is: -The late finish time (LF) for job B is The critical path is: The minimum time required to complete the project is: -The slack at activity E is: Immediate Predecessors Activity A B D E F G A .c A DE DF Activity Time 5 days 10 days 9 days 7 days 4 days 3 days 3 days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
