Question: B A E E MRP Example Complete the MRP planning schedule below. Lead time is 1 week and safety stock is 0. 50 pieces are

B A E E MRP Example Complete the MRP planning

B A E E MRP Example Complete the MRP planning schedule below. Lead time is 1 week and safety stock is 0. 50 pieces are on order to arrive in period 1. (a) First use order policy of Lot-for-lot. (b) Then use EOQ of 50. Period: 2 3 4 5 40 10 10 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases