Question: b) A process is designed to operate 2 shifts per day and 10 hours shift to produce 4500 units per day. Set up and maintenance

b) A process is designed to operate 2 shifts per day and 10 hours shift to produce 4500 units per day. Set up and maintenance times have been estimated to be 20% of total time available for the machine. Actual output of the machine has been 170 units/hour. The process operates 30 days per month and 7 days per week (4 Marks).

Compute the following:

1. Design capacity of the process per year

2. Effective capacity of the process per year

3. The utilization of the process

4. The efficiency of the process