Question: b . ) A project commenced in January and is planned to be completed in 1 0 months at a cost of f 1 0

b.) A project commenced in January and is planned to be completed in 10 months at a cost
of f1000 per month. After 6 months the planned value (PV) is estimated to be 6000, the
project is 68% completed, and the actual expenditure, actual cost (AC), is 5500.
Determine the status of the project after 6 months.
c.) You are the project manager on a project. The project is expected to be completed in
10months at a planned cost of f1000 per month. After 6 months the project is 55%
completed. The planned value after 6 months is f6000, and the actual certified
expenditure after 6 months is f6750. Determine the status of the project after 6 months.
d.) Explain your results, i.e., the S-curve produced in both question 2b and question 2c.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!