Question: B ) A project is set to be completed in 1 0 months with an estimated cost of $ 5 0 0 , 0 0

B) A project is set to be completed in 10 months with an estimated cost of $500,000. The project has been running for 5 months now, the tearn has spent $220,000 and completed an amount of work worth S255,000. What is the status of the project in terms of schedule, ahead or behind schedule?